Sunroc maintained extremely tight survey control with verified control points approximately every 1000.’ A combination of 3D GPS control and Total Station control was used to fine-tune the finish grade elevation of the subbase and base.

Sunroc used innovative methods on this project, including the following: This project consisted of a Full Runway 2-20, Runway 8-26 Reconstruction and RSA Safety Grading, completed in phases to accommodate the local SUU aviation school and local FedEx deliveries. With a dated lighting system and a nonstandard longitudinal slope, the runway in 2020 was due for a complete reconstruction. The current runway was last rebuilt in 1989, with an overlay performed about 11 after that added another decade to its lifespan.

Sunroc teamed up with Cedar City Corporation to rebuild the Cedar City Regional Airport.